Manager - Metro & Tunnels, TATA Projects Ltd.
Chennai Metro Rail Phase-2, TU-01 Project | 2022 - 2023
- Created the Management Information System (MIS) which illustrates the financial & physical progress of the project, hindrances to the project, and the estimated penalties & claims.
- Prepared the application for Extension of Time (EOT) for the project based on relevant contract provisions.
- Drafted Outgoings to the Employer, Engineer, and third parties on various subjects and prepared responses to the Incomings as per the relevant clauses of the contract.
Executive Trainee, TATA Projects Ltd.
Chennai Metro Rail Phase-2, TU-01 Project | 2021 - 2022
- Worked in the Procurement, Planning, Execution, Design, and Contracts Team of a $260 M metro rail project.
- Involved actively in the construction of diaphragm walls using a trench cutter and bentonite slurry setup.
- Responsible for procuring items, a total worth of ~$125k, for the project through systematic rate analysis and vendor management.
- Created a Daily Progress Report (DPR) in Excel that tracks the daily progress and optimized the DPR by linking the physical progress with financial progress.
- Devised Catchup Programs for sites using Primavera P6 to improve the rate of progress.